BEAD EHP Readiness Checklist

BEAD EHP Readiness Checklist
BEAD-funded construction cannot start until NTIA confirms environmental review is complete, so the fastest way to break ground is to have this information ready before review begins. Every BEAD subgrant includes conditions requiring NTIA approval of environmental review before construction, timely NEPA documents and permits, and a viable NEPA milestone schedule (NTIA). Use this BEAD EHP checklist to gather what your state broadband office and environmental team will ask for. Requirements vary by state, so confirm details with your state office.
Project and Funding Information
Subgrantee name, primary contact, and authorized representative
BEAD award or application ID and the state broadband office contact
Total project cost, BEAD share, and match sources
Any other federal funding or permits on the project (for example USDA, FCC, or USACE), which can affect who leads the review
Technology type: fiber, fixed wireless, or other
Number of broadband serviceable locations (BSLs) served
Target construction start, completion dates, and any seasonal work limits
Draft NEPA milestone schedule covering consultations, permits, NEPA, Section 106, and Section 7 reviews; NTIA's sample conditions call for a draft within 30 days of signing (NTIA
Route Maps and Location Data
Preliminary route maps and facility locations, including hubs, cabinets, huts, and towers
GIS files (shapefile or KMZ) of all routes, sites, and BSLs
Project plan drawings, even if preliminary
Staging, laydown, and equipment storage areas
Access roads, new or existing
Rights-of-way: road, railroad, or utility corridors, and any new easements
Land ownership along the route, flagging federal and tribal lands
Crossings of rivers, streams, wetlands, and federally managed waterways
Ground-level and aerial photos of the project area
States commonly ask for route maps, drawings, photos, and whether work touches federal lands or waterways (ConnectMT EHP Guide).
Construction Methods and Ground Disturbance
Installation method for each segment: aerial on existing poles, directional boring, plowing, trenching, or micro-trenching
Miles or feet of each method
Depth and width of disturbance for buried work
Bore entry and exit pit locations and sizes
Whether work stays in previously disturbed areas such as road shoulders and existing utility corridors, or crosses undisturbed ground
Tree clearing or vegetation removal, with approximate acreage and timing
Stream and wetland crossing methods (for example boring under versus open cut)
Erosion and sediment controls and site restoration plans
Handling of drilling fluids and spoil material
Work that stays in previously disturbed areas is more likely to qualify for a Categorical Exclusion. Undisturbed ground, waterbody crossings, and clearing usually need more review.
Structures, Towers, and Heights
New poles: number, locations, and heights
Pole replacements or extensions, with existing and new heights
New towers: location, height above ground, structure type, and lighting
Antennas or equipment added to existing structures, and whether the height increases
Equipment shelters, cabinets, and huts: footprint and foundation type
Distance from any tower or tall structure to the nearest airport or heliport, for FAA Form 7460-1 screening
Radio-frequency (RF) exposure information for wireless sites
Any FCC tower registration or review already started
Tower and antenna work can trigger FAA, FCC, historic preservation, and migratory bird reviews, so list every new or taller structure.
Known Resources, Permits, and Contacts
FEMA flood map with the project overlaid
USFWS National Wetlands Inventory map with the project and buffer zones overlaid
USFWS IPaC species list for the project area
Known historic, archaeological, or tribal resources near construction, and any early SHPO or THPO contact
Known contaminated or hazardous sites along the route
List of permits needed and their status: road and railroad crossings, utility pole attachments, USACE, state environmental, and local permits
Contacts for landowners, utilities, and local agencies already engaged
Any community concerns or controversy raised so far
These items flag the extraordinary circumstances that can move a project from a Categorical Exclusion to an EA: sensitive areas, protected species, historic or sacred sites, floodplains, wetlands, and hazardous waste (ConnectMT EHP Guide).
What Can Start Before Review Is Done
Until NEPA, Section 106, and ESA or Clean Water Act consultations are complete, BEAD funds cannot be used for site preparation, demolition, construction, or ground disturbance. Planning, permit applications, environmental studies, consultation support, limited preliminary procurement, and right-of-way leases can proceed (NTIA).
How WBE Helps
WBE turns this information into the EHP package your state office needs: desktop screening, field surveys, Categorical Exclusion documentation or EAs, and Section 106 and Section 7 coordination. Clients can follow review status, agency correspondence, and deliverables in NEPATracker™. This checklist is general guidance, not legal advice.