Section 106 Overview

15 hours ago
3 min read
Section 106 Overview resource guide over sunset main street with historic brick buildings, lit storefronts, railroad tracks, and utility poles.


Section 106 of the National Historic Preservation Act (NHPA) requires federal agencies to consider how their projects affect historic properties before work begins. Historic properties are buildings, structures, objects, districts, or archaeological sites listed on or eligible for the National Register of Historic Places (NTIA). Any project with federal funding, a federal permit, or federal land involvement is subject to it, including privately built projects funded through programs like BEAD. Section 106 runs alongside NEPA, and it must be finished before an agency can sign a Finding of No Significant Impact for an Environmental Assessment.


Who's Involved

Participant

Role

Federal agency (for example NTIA, FCC, USDA, or USACE)

Legally responsible for the review, findings, and government-to-government consultation with tribes

Applicant or grant recipient

Starts the review and identifies and assesses historic properties, often through a qualified consultant

State Historic Preservation Office (SHPO)

Reviews the project and comments on its effects

Tribal Historic Preservation Office (THPO) and tribes

On tribal lands, a THPO may act in place of the SHPO; tribes are consulted on places of religious and cultural significance on and off tribal lands

Advisory Council on Historic Preservation (ACHP)

Oversees the process, issues guidance, and approves program alternatives that streamline review

Other consulting parties and the public

Local governments, landowners, preservation groups, and interested members of the public


For BEAD, NTIA has authorized recipients to start reviews, identify properties, and assess effects from January 2024 through December 2030, while NTIA keeps responsibility for final determinations and tribal consultation (NTIA).


The Four Steps

  1. Initiate. Define the project and its Area of Potential Effects (APE), then notify the SHPO and the federal agency with a project description and maps. The agency also starts tribal notification.

  2. Identify historic properties. Review existing records and, where the SHPO requires it, survey the APE. Surveys must be done by professionals who meet the Secretary of the Interior's qualification standards.

  3. Assess effects. Make a finding of no historic properties affected, no adverse effect, or adverse effect. When the submission includes enough identification information and a finding, the SHPO has 30 calendar days to comment.

  4. Resolve adverse effects. If effects cannot be avoided, the agency, SHPO, ACHP, and consulting parties agree on mitigation in a Memorandum of Agreement (MOA).


Review is complete when the SHPO concurs with a finding of no effect or no adverse effect and tribal outreach is done, or when all parties sign an MOA (NTIA).


Tribal Consultation

Federally recognized tribes are sovereign nations, so the federal agency consults with them government to government. Applicants and consultants support that consultation but cannot replace it.

  • Off tribal lands: Tribes are consulted on places of religious and cultural significance, including sites far from current reservations. For BEAD, NTIA sends state-based notifications to tribes; tower projects use the FCC's Tower Construction Notification System (TCNS).

  • On tribal lands: The tribe's own requirements apply, and projects must be reported to NTIA right away.

  • Timing: Tribal outreach typically concludes in 30 to 45 days unless a tribe identifies potential adverse effects (NTIA).

  • Confidentiality: Information about sacred sites and archaeological locations is sensitive and is not shared publicly.


Respond promptly to tribal requests, share project maps and descriptions, and keep records of every substantive contact.


Section 106 for Broadband and Telecom Projects

Two tools can shorten review for communications projects:

  • ACHP Program Comment for Federal Communications Projects: First issued in 2017 for federal lands, it was amended in March 2024 at NTIA's request to cover communications projects by any federal agency, on or off federal lands (NTIA). It streamlines how historic properties are identified, and some activities, such as certain collocations and work in existing rights-of-way, can qualify for exclusions.

  • FCC Nationwide Programmatic Agreements: Wireless towers and antenna collocations follow the FCC's agreements, with review started through the FCC's E-106 and TCNS systems. The federal funding agency still reviews non-tower infrastructure such as fiber.


Whether either tool applies depends on the project, so confirm with the lead agency before relying on it.


How WBE Helps

WBE's cultural resources team defines the Area of Potential Effects, conducts records searches and field surveys, prepares findings of effect, and manages correspondence with SHPOs, THPOs, and tribes. This overview is general information, not legal advice.


Sources


Comments


markets-background-contour-lines.png

proud member of the: 

LET'S DISCUSS YOUR PROJECT.
memberCeLogo_small (1)_edited.png

7707 E. 111th St, Suite 101, Tulsa, OK 74133, USA

(918) 660-0999

  • facebook
  • googlePlaces
  • twitter
  • linkedin

©2026 by White Buffalo Environmental, Inc..

Your request has been received. Thank you!

bottom of page